  • Alternative Energy Solutions
    • Mountain House (P104CT)
        New Upmarket Residential Property
        Client name Confidential
        Location Oranjezicht, Cape Town
        Office responsible Cape Town

        Mapule Consulting Responsibilities

        Verify design of PV solar contractor, check calculations and perform site supervision for 25kWp PV solar installation at an existing high end residential property for which Mapule Consulting was the Electrical Consulting Engineers during the original construction of the residence.

        The system allowed for a combination of grid tie and hybrid inverters with battery back-up, some of which formed part of the original project.
  • Building Services
    • Johnson & Johnson (Pty) Ltd (P190CT)
        Upgrade of existing Admin Office Block including stripping out of all existing services and re-installation of new modern offices and meeting rooms.
        Client name Johnson & Johnson (Pty) Ltd
        Location Retreat, Cape Town
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        Full electrical design including lighting, small power, fire detection evacuation control, access control and services accommodation for telephone / data and AV installations.
    • Hylton Ross Pomona (P241CT)
        Hylton Ross, Springbok Atlas & IKAPA regional bus storage and maintenance terminals.
        Client name Mottola Property Investment (Pty) Ltd
        Location Pomona Johannesburg
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        Full electrical design including generator refurbishment, UPS, CCTV, electric fencing and data.
    • Heideveld Primary School (P208CT)
        New Primary School is a replacement school as part of the Department of Basic Education’s Accelerated School Infrastructure Development Initiative Programme.
        Client name Provincial Government Western Cape
        Location Heideveld Western Cape
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        Full electrical design, lighting, data, alarm system and intercom design.
        Photo compliments of Meyer & Associates Architects, Urban Designers.
  • General Specialized Fields
    • Orica Explosives Manufacturing Plants (P199CT)
        Rapid deployment explosives manufacturing plants for mining applications mainly in Africa and also in Europe.
        Client name Orica Africa (Pty) Ltd
        Location Ghana, DRC, Tanzania, Mozambique, Bulgaria
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        Development of electrical component of Containerised explosives manufacturing plant inclusive of electrical reticulation, site and facilities lighting, earthing as well as lighting protection. Site lighting and lightning protection of magazine sites are also included with the scope of services and responsibilities.

        Modifications to an existing fixed process plant in Bulgaria inclusive of instrumentation, MCC and operator control panel design with preference for relay logic also formed part of the Mapule Consulting responsibilities.
  • High End & Residential
    • New Upmarket Residential Property (P188CT)
        High End Residential Development with Home Automation.
        Client name Confidential
        Location Cape Town
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        Full electrical design including generator.
        UPS and alternative power.
        Home automation.
        Assisting Architect with lighting design.
        Electrical, standby power, home automation, access control, CCTV, security and AV installations.
  • Lighting Design
    • Warehouse and Site Security Lighting Upgrade (P272CT)
        Replace HID based lighting installation on block switching with LED solution and occupancy sensors to achieve improved lighting levels with excellent horizontal and vertical uniformity and energy savings.
        The outdoor / security lighting upgrade involved the replacement of all external HID based lighting with LED lighting.
        An electricity demand improvement of 40% and consumption reduction of 72% was achieved for the warehouse lighting and 38% saving in consumption for the outdoor / security lighting.
        Client name Johnson & Johnson (Pty) Ltd
        Location Retreat, Cape Town
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        Design, contract administration, site supervision and verification of energy savings.
  • Pharmaceutical
    • Project Phoenix (P191, P201, P202, P205CT)
        Upgrade of Liquids Manufacturing Department, Packaging Department, new QC and Micro-Laboratories and new RO Plant Room of an existing pharmaceutical manufacturing facility, keeping the plant in operation during the upgrade.
        Client name Johnson & Johnson (Pty) Ltd
        Location Retreat, Cape Town
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        Consulting engineering services for electrical building services including lighting, small power, fire detection, evacuation control and door interlocking to maintain pressure cascading of the clean room facilities.

        Mapule Consulting was also instrumental in the development of a special clean room light fitting through dealings with a Cape Town based manufacturer of light fittings.

        Our responsibilities also included the hazardous area zoning for the project.
  • Specialized Installation
    • Johnson & Johnson Liquids Manufacturing (P201CT)
        Part of Project Phoenix
        Hazardous area zoning of the Liquids Manufacturing Department upgrade to ensure compliance with SANS requirements and satisfaction of J&J's insurers.
        Client name Johnson & Johnson (Pty) Ltd
        Location Retreat, Cape Town
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        Compile report and drawings to indicate hazardous area classification for the project.
  • Standby Power
    • Hylton Ross Pomona (P241CT)
        Hylton Ross, Springbok Atlas & IKAPA regional bus storage and maintenance terminals including offices.
        Client name Mottola Property Investment (Pty) Ltd
        Location Pomona Johannesburg
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        Emergency and UPS power calculations, refurbishment and existing generator canopy specifications including new changeover system and UPS specification.
    • Hexkoel Generators
        Modular installation of 4 x 500kVA auto-synchronising standby generators in multiple soundproofed generator rooms with ultimate design capacity of 2,5MVA. Standby power is stepped up to 11kV change-over at Eskom supply point with break before make transition for distribution to the Cold Room facility 11kV network.
        Client name Hexkoel (Pty) Ltd
        Location De Doorns
        Office responsible Mapule Consulting Cape

        Mapule Consulting Responsibilities

        All consulting engineering services (structural and architectural work subcontracted).
        Principle agent.
        Cost & construction program control.
        Protection settings and relay coordination for the site, when operated from utility supply and from generator supply.
        Negotiations with power utility.